The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
1
11.67 Months
2
10.67 Months
3
9.67 Months
4
8.67 Months
02
PYQ 2023
medium
construction-and-management ID: cuet-pg-
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
1
6 months
2
6.5 months
3
7 months
4
7.5 months