A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
JobProcessing Time
P5
Q2
R2
S2
T1
Schedule that minimizes total inventory cost is:
1
T-S-Q-R-P
2
P-Q-R-S-T
3
T-R-S-Q-P
4
T-S-R-Q-P