A set of 5 jobs is to be planned on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs.2 per day.
Schedule that minimizes total inventory cost is:
| Job | Processing Time |
| P | 5 |
| Q | 2 |
| R | 2 |
| S | 2 |
| T | 1 |
1
T-S-Q-R-P
2
P-Q-R-S-T
3
T-R-S-Q-P
4
T-S-R-Q-P