11 MCQs

01
PYQ 2023
medium
mathematics ID: cuet-pg-
Ram and Mohan can do a piece of work in 20 days. Mohan alone can do the work in 30 days. In how many days will Ram alone complete the work.
1
60 days
2
50 days
3
40 days
4
30 days
02
PYQ 2023
medium
mathematics ID: cuet-pg-
Akhil is two times as efficient as Vinod and Kamal is three time as efficient as Vinod. They worked together and received ₹ 5,700 for doing the work. Find the share of Kamal in the money received.
1
₹ 1800
2
₹ 1900
3
₹ 2580
4
₹ 2850
03
PYQ 2023
hard
mathematics ID: cuet-pg-
Pipes A and B can fill a tank in 25 hours and 10 hours respectively. Pipe A was opened and after half an hour pipe B was also opened. In how much time the tank got filled?
1
7 hours 10 minutes
2
7 hours 15 minutes
3
7 hours 30 minutes
4
7 hours 45 minutes
04
PYQ 2023
hard
mathematics ID: cuet-pg-
3 boys and 5 girls can complete one work in 8 days. 7 boys can complete the work in 4 days. Number of girls required to finish the work in half day is:
1
940
2
280
3
560
4
412
05
PYQ 2023
hard
mathematics ID: cuet-pg-
Twelve men can do a work in 8 days and 16 women can do the same work in 12 days. Eight men and 8 women worked together for 6 days. How many additional men need to be employed to complete the remaining work in one day?
1
8
2
9
3
12
4
15
06
PYQ 2023
medium
mathematics ID: cuet-pg-
Ram has a sum of money, which is sufficient to pay either Usha's wages for 30 days or Manika's wages for 60 days. If he employes them together, the money is sufficient to pay their wages for how many days?
1
30
2
20
3
12
4
10
07
PYQ 2023
medium
mathematics ID: cuet-pg-
Five men working 8 hours per day take 6 days to do a work. How many days will 12 men take to do the same work if they work for 10 hours per day?
1
2
3
3
4
2
08
PYQ 2023
medium
mathematics ID: cuet-pg-
Two pipes A and B can fill a tank in 18h and 12h respectively. If both the pipes are opened simultaneously, then how much time will be taken to fill the tank
1
h
2
h
3
h
4
h
09
PYQ 2023
medium
mathematics ID: cuet-pg-
10 men and 15 women can do a work in 6 days. One man can do the work in 100 days. In how many days can a woman do the work?
1
90 days
2
125 days
3
150 days
4
225 days
10
PYQ 2023
medium
mathematics ID: cuet-pg-
A water tank can be filled by two pipes P and Q in 60 minutes and 30 minutes respectively. How many minutes will it take to fill the empty tank if pipes P and Q are opened for first half of the time, after which only pipe Q is opened for next half of the time?
1
14
2
25
3
35
4
24
11
PYQ 2023
medium
mathematics ID: cuet-pg-
Two pipes A and B can fill a tank in 15 minutes and 20 minutes respectively. Both the pipes are opened together but after 4 minutes, pipe A is turned off. What is the total time taken to fill the tank?
1
14 min 40 sec
2
12 min 30 sec
3
11 min 45 sec
4
10 min 20 sec