Sequentially arrange the steps involved in laying a sewer line:

A. Transferring the center line of the sewer to the bottom of the trench.
B. Setting sight rails over the trench.
C. Driving pegs to the level of the invert line of the sewer.
D. Placing the sewer in the trench.
Choose the most appropriate answer from the options given below:

1
A, B, C and D
2
B, C, D and A
3
B, D, C and A
4
B, C, A and D