Which type of contract is not suitable for difficult foundations, excavation of uncertain character, and projects susceptible to unpredictable hazards and variations?
1
Lump Sum Contract
2
Item Rate Contract
3
Cost Plus Fixed Fee Contract
4
Running Contract
02
PYQ 2024
medium
water-engineering-and-management ID: cuet-pg-
Out of the following, which drawing together with other documents like the bill of quantities, describes the project scheme to the contractor so that he can price the construction work accordingly?
1
Contract Drawing
2
Tender Drawing
3
Working Drawing
4
Completion Drawing
03
PYQ 2024
medium
water-engineering-and-management ID: cuet-pg-
Which construction stage is required to carry out technical investigations such as soil investigation, topographic investigation, material supply, and market survey, etc.?
1
Report Stage
2
Planning Stage
3
Tendering Stage
4
Construction Stage
About Construction Management - CUET-PG
Construction Management is a vital chapter for CUET-PG aspirants. Mastering the concepts covered in this chapter is essential for securing a top rank.
By rigorously practicing the previous year questions associated with this chapter, you can identify high-yield topics, understand the examiner's perspective, and boost your confidence during the actual exam.
Frequently Asked Questions
Why focus on Construction Management PYQs?
Analyzing PYQs for this specific chapter reveals the most frequently tested concepts and the typical complexity of questions, allowing you to tailor your study plan efficiently.
How to best use this analysis?
Review the topic breakdown to see which sub-topics within Construction Management carry the most weight. Then, tackle the questions iteratively to solidify your understanding.