What will be the expected time for driving the precast piles for a bridge abutment activity having optimistic time 22, most likely time 30, and pessimistic time 50?
1
34 days
2
32 days
3
42 days
4
40 days
02
PYQ 2025
easy
water-engineering-and-management ID: cuet-pg-
The reduction in project time normally results in
1
Increasing the direct cost and decreasing the indirect cost
2
Decreasing the direct cost and increasing the indirect cost
3
Increasing the direct cost and the indirect cost both
4
Decreasing the direct cost and the indirect cost both