10 previous year questions.

Volume: 10 Ques
Yield: Medium

High-Yield Trend

8
2025
2
2024

Chapter Questions
10 MCQs

01
PYQ 2024
medium
general-aptitude ID: cuet-ug-
Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do 1/4 of the job working together?
1

8 days

2

6 days

3
10 days
4
12 days
02
PYQ 2024
medium
general-aptitude ID: cuet-ug-
A tap can fill a tank in 6 hours. After half the tank is filled, three more similar taps are opened. What is the total time taken to fill the tank completely?
1
4 hours
2
5 hours
3
3 hours 30 minutes
4
3 hours 45 minutes
03
PYQ 2025
hard
general-aptitude ID: cuet-ug-
A and B can complete a task in the ratio 3:2. If together they complete the task in 20 days, how long will A alone take?
1
30 days
2
32 days
3
36 days
4
40 days
04
PYQ 2025
hard
general-aptitude ID: cuet-ug-
A and B together can complete a task in 10 days. A alone can finish it in 15 days. In how many days can B alone finish the work?
1
20 days
2
25 days
3
30 days
4
40 days
05
PYQ 2025
medium
general-aptitude ID: cuet-ug-
P and Q can complete a job in 24 days working together. P can alone complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining job is:
1
26 days
2
30 days
3
64 days
4
60 days
06
PYQ 2025
easy
general-aptitude ID: cuet-ug-
If 5 workers can complete a job in 12 days, how long will 8 workers take to complete the same job (assuming all work at the same rate)?
1
6 days
2
7.5 days
3
8 days
4
9 days
07
PYQ 2025
medium
general-aptitude ID: cuet-ug-
Two pipes can fill a tank in 20 hours and 30 hours respectively. A third pipe empties the tank in 15 hours. If all three pipes work together, how long will it take to fill the tank?
1
12 hours
2
15 hours
3

60 hours

4
20 hours
08
PYQ 2025
medium
general-aptitude ID: cuet-ug-
A can complete a job in 12 days and B in 15 days. They work together for 5 days, and then A leaves. How many more days will B take to finish the remaining work?
1

3.75

2
5
3
3
4
6
09
PYQ 2025
easy
general-aptitude ID: cuet-ug-
A and B can do a work in 12 days and 15 days respectively. How long will they take to complete the work if they work together?
1

6 days

2
7 days
3
8 days
4
5 days
10
PYQ 2025
hard
general-aptitude ID: cuet-ug-
A man can complete a job in 12 days. How many days will it take for 3 men to complete the same job, assuming they work at the same rate?
1
3
2
4
3
6
4
8